NTPC under-recovery flags coal supply crisis

NTPC under-recovery flags coal supply crisis

That a large part of NTPC’s reported under-recoveries of Rs210 crore in Q2FY19 was due to unavailability of coal exacerbated the coal supply crisis in the country. The company had reported Rs 1,400 crore of under-recovery in FY18, of which Rs800 crore was due to coal shortage.

The company’s net profit slipped 1.1% year-on-year (y-o-y) to Rs2,417.6 crore in the quarter. Fuel stock at NTPC’s power plants remains low with current coal stock of 3.7 MT from a high of 6.9 MT.

“Though NTPC’s earnings prospects appear bright due to capacity addition and rise in regulated equity, this will be overshadowed by ongoing under-recovery due to coal shortage that will dampen core return on equity,” Axis Capital said in a recent report.

In the first half of FY19, NTPC’s under-recovery due to coal shortage at 2,320 MW Mouda plant, 2,000 MW Simhadri station and 2,400 MW Kudgi unit was `156 crore, `78 crore and `25 crore, respectively.

Maintenance activities at the 1,550 MW Unchaahar plant — where 45 people had died last year in a boiler blast — also led to under recoveries of `131 crore in the quarter. The management expects the plant to be come operational by December 15.

NTPC had received 168.5 MT coal in FY18, which includes 0.32 MT of imports. Requirement for FY19 is estimated to be 196.3 MT.

NTPC had received 168.5 MT coal in FY18, which includes 0.32 MT of imports. Requirement for FY19 is estimated to be 196.3 MT.

Power plants are contractually entitled to receive fixed costs (capacity charge) for recovering capital expenses even when buyers do not procure electricity from these units. However, plants need to display a minimum plant availability factor (PAF) of 83% to claim fixed costs.

The average PAF of NTPC plants in Q2FY19 dropped by nearly two percentage points y-o-y to 84.3%, mainly due to coal shortage and planned outages for maintenance. NTPC is facing coal shortages even as its private peers are complaining about absence of level playing field in the sector in terms of fuel supply.

Independent power producers have pointed out multiple times that preferential coal allocation and supplies to NTPC plants was one of the reasons behind more than 40,000 MW of private power plants becoming stressed.

To tackle the domestic fuel shortage, NTPC is subscribing to Coal India’s offer to procure additional coal from mines through roadways. It has also paid Rs10,000 crore in advance to the railways to receive coal supply at unrevised rates until FY20. Through this, NTPC has already hedged itself against the recent 8.8% rise in railway freight cost of coal.

The company is also working on five captive blocks with mining capacity of 56 MT per annum. It has been allotted 10 blocks with potential to produce 111 MT of the fuel every year.

NTPC has already extracted 2.5 MT coal from Pakri Barwadih mine in the first six months of FY19, against the annual production target of 6.3 MT. Additionally, 4,000 tonne have been produced from the Dulanga mine, which expects to produce 1.7 MT in FY19.

NTPC has also floated a tender to import 2.5 MT of coal, but the state-owned company risks being seen as an import driver as the country desperately tries to cut import bills amid the rupee devaluation.

India’s coal import went up from 171 MT in FY14 to 208 MT in FY18. High-calory Indonesian coal now costs about $101/tonne, 7.3% higher than a year ago. Coal prices in rupee terms recorded a price rise of 23.4% to `7,066/tonne in the same period.