Crack down on delays in Coal India projects
Posted on 22nd January 2019
The delay in timely completion of Coal India projects worth Rs 11,000 crores is a matter of concern, not just because it aggravates the coal shortage but also leads to increasing project costs. India, for instance, imports over 200 million tonnes of coal a year, with a huge outgo of foreign exchange. It’s a Catch-22 situation, because while India has a lot of coal resources, other issues like getting environmental clearances and land acquisition, among other things, are monumental hurdles. The Narendra Modi government has tried various ways of combating these delays. There is a whole department like the Online Computerised Monitoring System in the ministry of statistics and programme implementation to track the progress of projects, in addition to the setting up of a revised cost committee for fixing responsibility for time and cost overruns, and to regularly review infrastructure projects. Despite this, around 253 of 1,332 projects are running behind schedule. The loss to the public exchequer is estimated at Rs 2.23 lakh crores, as costs escalated from Rs 16,26,675.52 crores to Rs 18,49,766.91 crores.

India, with 55 per cent delays, is one of the worst performers as far as delayed projects are concerned, followed by countries like China, Bangladesh and Thailand. The power sector faces the most delays, accounting for 61 of the 114 projects, followed by the railways, with 46 out of 330 projects facing delays.

The government needs to tackle this problem either sector-wise or case by case. There was an earlier decision to give sanctions only to those projects that had fulfilled all requirements of getting environmental clearances, land and whatever else is required. The fate of this decision is not known.

Globally, there is a move to avoid using coal as a source of energy due to environmental issues, and perhaps India should do the same. India is blessed with sunshine almost 365 days of the year, and should go in for the use of renewable energy. Solar and wind energy is ideal, and this should be taken up on a mass scale. The costs of both solar and wind energy are now almost down to that of electricity. It is really a matter of regret, therefore, that they are not being used on the scale that is needed. They are still treated as something esoteric. Perhaps coal minister Piyush Goyal can discuss this issue with his colleagues in the relevant ministries.

To cut down on the import of coal due to the poor quality of Indian coal, the government should think of acquiring the technologies available to clean coal and remove or reduce the pollutant emissions. Globally, chemicals are used to wash minerals and impurities from coal and treat flue gases to remove pollutants. They reduce the emissions of ash and sulphur dioxide while the coal is burned.

Related Companies: Coal India Ltd   

Other Latest News
Adani Gas crashes 14% on report of gas regulator's notice on non-disclosure
Posted on 24th January 2020

Shares of Adani Gas slipped 14 per cent to Rs 148 on the BSE in Friday's session on reports that Petroleum and Natural Gas Regulatory Board of India (PNGRB) has sent a notice to the company for failing to disclose crucial information regarding a scheme of arrangement with Adani Enterprises.

According to the report by TV channel CNBC Awaaz, Adani Gas has bid for gas projects using networth calculations of Adani Enterprises and that the company’s shareholding changes and restructuring violated city gas distribution regulations.


Shiv Sena questions Centre on democracy ranking drop, economic woes
Posted on 24th January 2020

The Shiv Sena on Friday said there have been attempts to muzzle dissenting voices and this is one of the reasons for India slipping in the 2019 Democracy Index’s global ranking. An editorial in Sena mouthpiece Saamana said a slowdown in economy gives rise to unrest and instability, and this was getting reflected in the prevailing situation in the country.

Now (after an economic slowdown) there is a slide in (India’s) global democracy index ranking, the Marathi daily said.


Grilled on CAA at WEF, Goyal says Muslims in India safer than anywhere else
Posted on 24th January 2020

Union minister Piyush Goyal on Thursday said Muslims in India are safer than most places in the world.

India is probably one of the most inclusive societies in the world, Goyal said here at a session on 'Strategic Outlook: India' at the WEF 2020.


Judge who issued death warrants against Nirbhaya rapists transferred to Supreme Court registry
Posted on 24th January 2020

A Delhi court judge who issued death warrants for all four convicts in Nirbhaya case has been transferred to the Supreme court registry.

Judge Satish Arora has been appointed as additional registrar in the Supreme Court on a deputation for a year.

Satish Arora had been hearing the petition of parents of Nirbhaya seeking to expedite the process of execution.


Companies announce clinical trials for vaccine against China virus
Posted on 24th January 2020

Clinical trials for a vaccine against the new virus sweeping China could be carried out in the summer, the head of an anti-epidemic coalition said on Thursday, as different companies announced research into the disease.

We can announce that we have three partnerships to develop vaccines against the novel coronavirus, Richard Hatchett, chief executive of the Coalition for Epidemic Preparedness Innovations (CEPI), said in Davos.


» Post a FREE Classified Advertisement
Inviting Real Estate Agents, Job Placements Agents, Educational Institutes, Software Service Providers, Real Estate Builders, Marriage Bureaus, Travel Agents, Restaurant Owners, Health & Fitness Centers and other Local Businesses to Post a FREE Classified Advertisement on Cootera.com Classifieds Website.
Jobs in India India Real Estate Automobiles Matrimonials Beauty & Fitness

Add a comment for Crack down on delays in Coal India projects
Please only use this form to enter comments on the above company. All comments are reviewed before they are displayed on the web site. Not all comments may be displayed. Check back with us to see if your comments have been displayed.
If you want us to email the comments posted by users, please Subscribe by email
Name*
Comments*
Security Code*
 

Be the first person to write a business review for Crack down on delays in Coal India projects

Most Read News

HCL Tech falls 5% from day's high on profit booking post Q3 results

Citizenship Act: SC refuses to grant stay, gives Centre four weeks to reply

India ranks 76th on WEF's Social Mobility Index, Denmark tops the list

HDFC Bank slips over 1% as Q3 provisions rise; analysts maintain 'Buy'

Adani Enterprises denies wrongdoing in coal supply contracts case

More India News

  India Web Directory
Business Profiles
Automotive Directory
IT/ITES/BPO Directory
Hotel Directory
Health Directory
Business Directory
Gems & Jewellery
Education Directory
Real Estate Directory
Agriculture Directory
Logistics Directory
Yellow Pages
NRI Guide
Photo Galleries
Global Web Directory
*** FREE India Classifieds
Order Premium Listings
Submit a Site
Business Reviews
Home
About us
Link to us
Advertise
Contact us
Google Search Keywords: India Catalog, IndiaCatalog, India Web Directory
    © 1999 - 2020 IndiaCatalog.com
    All Rights Reserved
Privacy Statement